Uploaded image for project: 'Campaign Manager'
  1. Campaign Manager
  2. CAMPMAN-23

Calendar ignores start date

    XMLWordPrintable

Details

    • Bug
    • Resolution: Fixed
    • Major
    • 3.1.4
    • 3.1.3
    • None

    Description

      Steps to reproduce

      1. Schedule campaigns in the same month with staggered start dates (See attached for example).
      2.  Open Calendar

      Expected results

      1. It is reasonable to expect the calendar to acknowledge the specified start dates.

      Actual results

      1. Seemingly all events active in a given month are displayed. The configured start date is ignored.

      Development notes

      See attached screenshots for examples from a supermarket demonstration. The campaign Comic Relief + Mothers' Day is due to start on 6th March and the campaign Easter + Comic Relief is due to start on 15th March. However, as shown in the calendar screenshot, both are displayed as valid for 2nd March.

      Checklists

        Acceptance criteria

        Attachments

          Activity

            People

              tmiyar Teresa Miyar
              chris.jennings Chris Jennings
              Votes:
              0 Vote for this issue
              Watchers:
              2 Start watching this issue

              Dates

                Created:
                Updated:
                Resolved:

                Checklists

                  Bug DoR
                  Task DoD

                  Time Tracking

                    Estimated:
                    Original Estimate - Not Specified
                    Not Specified
                    Remaining:
                    Remaining Estimate - 0d
                    0d
                    Logged:
                    Time Spent - 0.5d
                    0.5d